What’s Happening - 2018G

.

Work continues on the new Barungwarra boat ramp car park.

© B. Clifford for Bald Hills Bushies 2020 Tree beds are referenced by the name used by busties to identify them. Names and locations of these beds are indicated on the maps.
Sunday 25th November - The new storm water drain is now finished. Rocks are piled nearby to build a retaining wall. Kerbing is in place for the new roadway. Left picture, looking towards the river. Right picture looking towards the houses. The old boat ramp area has been re-profiled. Kerbing guides are in place around the new ramp. Saturday 1st December - Work is continuing on the roadway. Kerbing now extends to the boat ramp Thursday 12th December - Wok has started on installing the log barrier. The Island near the entrance is now in place. The Footath is now complwtw and turf has been laid around the path and along the edge of the car park. The old Boat Ramp area now has a rock wall. The Bitumen area and Kerbing joins the new ramp. The Drain area at the top od the driveway is complete. Current view of the 2 roads. Friday 14th December - A guard rail has been erected around the new drain.
Top Dressing and Turf has been laid over the old sandy area between the two paths. work is continuing on the log fence. The stone wall around the old boat ramp in now complete.
Link to What’s Happening 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023